Question
Asha bought a dress and sold it at a profit of 20%. Had
she bought it for Rs. 400 less and sold it for Rs. 480 more, she would have earned a profit of 60%. The original cost price of the dress is how much percent more than the reduced cost price of the dress?Solution
Let the original cost price of the dress be Rs. β100xβ. So the original selling price = 1.20 Γ 100x = Rs. 120x. Reduced cost price = Rs. (100x β 400). According to question: 1.60 Γ (100x β 400) = 120x + 480 160x β 640 = 120x + 480 40x = 1120 x = 28. So, the original cost price = Rs 2800 and the reduced cost price = Rs. 2400 So, the desired percentage = 400/2400 Γ 100 = 16.67%.
(y+15) men can do a piece of work in (z-30) days. (y-15) men can do the same piece of work in (z+45) days. If (y+25) men can do the same work in (z-45) ...
A and B are capable of completing a project individually in 40 days and 50 days, respectively. Initially, A and B collaborated on the project, and after...
A and B together can complete a piece of work in 55 days while B and C together can complete the same work in 66 days. All of three togeth...
- Ajay alone can finish 60% of a task in 18 days. Vijay takes 15 days longer than Ajay to complete the entire task. When Vijay and Chirag work together, they...
Anil and Ashish receive Rs.2000 for work of 8 days. If Anil is 4 times efficient than Ashish, then find the daily wage received by Ashish.
'Manoj' can complete some work alone in 40 days. 'Sohan' is twice as efficient as 'Rohan' and five times as efficient as 'Manoj'. If 'Manoj' and 'Rohan'...
A and B individually can complete the work in 30 days and 45 days respectively. If the time taken by C alone to complete the work is 1.5 times the time ...
P and Q can do a piece of work in 20 days and 12 respectively, P started the work alone and then after 4 days Q joined him till the completion of the wo...
V and N, working individually, can complete a task in (w β 2) days and (w + 4) days, respectively. N initiated the task alone and was later joined by ...
60 men can complete a piece of work in 12 days. 12 men started the same work and worked for 10 days, and then joined by βxβ more men such that the r...