Question
A can do a piece of work in 32 days and B in 48 days. They work together for 8 days and then A goes away. In how much time (in days) will B finish the 60% of the remaining work?
More Previous year papers Questions
- In a class, the number of girls is 30% more than the number of boys. The total number of boys and girls in the class is 92. If 4 more girls are admitted in...
- If the price item is increased by 70% and then allows a scheme discount of 5% and 20% on this marked price. If price is paid in cash and additional discoun...
- Simplify the following:
- A car can travel a distance of 300 meters in 6 minutes. What is its average speed in km/h?
- Average weight of 8 gold coins is 20 g per coin. Average weight of 12 silver coins is 35 g per coin. What is the average weight per coin for 20 coins?
- A man looks at the reflection of the top of the lamp-post on the mirror that is 6.6 m away from the foot of the lamppost. The man’s height is 1.25 m and he...
- What is the single discount equivalent to the successive discounts of 20%, 35%, and 10%?
- A person saves 18% of his income. If his income increases by 6.65% and his savings decrease by 20%, then by what percent will his expenditure increase?
- Find the amount received from compound interest (Rs.) At Rs.18,800 for 2 years at an annual rate of 10%.
- If sin²θ − cos²θ = −1/3, find the value of cos²θ.
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt