    P and Q can do a job in 90 days, Q and R can do it in

    112.5 days, while P and R can do it in 150 days. X is five times as efficient as P, Y is two-thirds as efficient as Q, and Z is 2.5 times as efficient as R. Determine the number of days required to complete the same job if X, Y and Z work together.
    A 30(28/29) Correct Answer Incorrect Answer
    B 31(3/29) Correct Answer Incorrect Answer
    C 31(2/29) Correct Answer Incorrect Answer
    D 31(1/29) Correct Answer Incorrect Answer

    Solution

    The correct answer is D