    A and B can do a work in 10 days and 40 days,

    respectively. How long will it take together to complete the work?
    A 12 days Correct Answer Incorrect Answer
    B 8 days Correct Answer Incorrect Answer
    C 15 days Correct Answer Incorrect Answer
    D 20 days Correct Answer Incorrect Answer

    Solution

    Work rates: A = 1/10 per day B = 1/40 per day Combined rate = 1/10 + 1/40 = 4/40 + 1/40 = 5/40 = 1/8 Time = 1 ÷ (1/8) = 8 days