    A and B can complete a piece of work in 8 days. B alone

    can do it in 12 days. If A alone starts the work and works for only 4 days and then leaves, then how many more days will B take to finish the remaining work?
    A 10 days Correct Answer Incorrect Answer
    B 12 days Correct Answer Incorrect Answer
    C 8 days Correct Answer Incorrect Answer
    D 9 days Correct Answer Incorrect Answer

    Solution

    The correct answer is A