Question
A and B can complete a piece of work in 8 days. B alone can do it in 12 days. If A alone starts the work and works for only 4 days and then leaves, then how many more days will B take to finish the remaining work?
More Previous year papers Questions
- 2/5 of marked price is equal to 3/4 of selling price. What is the discount percent?
- Riya sold a laptop for ₹35000, earning a profit of 25%. If she wanted to earn a profit of 30%, at what price should she have sold the laptop?
- Find the value of given expression. 30 – [40 – {56 – (25 – 13 – 12)}]
- After working for 8 days, Rakhi finds that only 10 percent of the work is completed. She employs Poonam who is 20 percent more efficient than Rakhi. How ma...
- The cost price of an article is Rs. x. It is marked up by 100 percent and it is sold at Rs. 420 after giving 30 percent discount. What is the value of x (i...
- Hema invested ₹1,728 at the rate of compound interest (Compounded annually) for 3 years. She got ₹4,096 after the specified period. Find the rate of intere...
- First four terms of a series are 4, 12, 36, 108. What will be the 6th term of this series?
- While listing N consecutive even numbers for determining their average, the last number, by mistake, got replaced by the next odd number and thereby the av...
- What least number be subtracted from 13983 to make it a perfect square?
- With an average speed of 50km/h, a train reaches its destination in time. If it goes with an average speed of 40km/h, it is late by 30 minutes to reach its...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt