Question
Following questions have two quantities as Quantity I
and Quantity II. You have to determine the relationship between them and give answer as Quantity I: A, B and C can do a piece of work in 16, 32 and 48 days respectively. In how many days can A do the work if he is assisted by B and C on every fourth day? Quantity II: A, B and C can do a piece of work in 12, 24 and 36 days respectively. In how many days work will be finished if they work on alternate days in the same order?ÂSolution
Quantity I:  Let total work = LCM of 16, 32 and 48 = 96 units A's 1 day work = 6 units, B's 1 day work = 3 units & C's 1 day work = 2 units Total work completed in 4 days = 6+6+6+(6+3+2) = 29 units So total work completed in 12 days = 87 units Total work in 13 days = 87 + 6 = 93 unit Rest 3 unit is completed by A in = 3/6 days = 1/2 days So total work completed in = 13 +(1/2) = 27/2 days. Quantity II:   Let the total work = LCM of 12, 24 and 36 = 72 units A's 1 day work = 6 units, B's 1 day work = 3 units & C's 1 day work = 2 units Total work completed in 3 days = (6+3+2) = 11 units Hence 11 units is completed in 3 days, So 66 units will completed in = 3 × 6 = 18 days Next day, A will come & will do 6 units more so workdone till now = 66 + 6 = 72 units So total work completed in = 18 + 1 = 19 days.
Working alone, 'C' can complete a job in 30 days. 'D' takes 20% less time than 'C' to finish the same job. Calculate the percentage of work done by 'C' ...
- If Riya takes three times the time that Mahi takes or four times the time that Neha takes to finish a task, and all three working together can complete it ...
- Pipes X and Y can fill a water tank individually in 24 minutes and 36 minutes, respectively. A third pipe Z can empty the tank in 72 minutes. If all three ...
A can complete a piece of work in 24 days. He worked for 21 days and then B finished the remaining work in 6 days. In how many days can A and B finish t...
A can complete a piece of work in 10 days , and B can complete the same work in 15 days . They start working together, and after some days A leaves....
The ratio of time taken by P, Q and R to complete work alone is 4:6:3 respectively. If all three together complete the work in 8 days, then find in how ...
18 women can do piece of work in 12 days. 12 men can do the same piece of work in 9 days. Find in how many days will 8 men and 8 women complete that work?
A and B together, B and C together and A and C together can complete a piece of work in 14 days, 15 days and 18 days respectively. Find the ratio of the...
Q can do a work in 15 days and R can do the two-third work done by P and Q together in a day. If R completes the work in 18 days, how many days will it ...
A' can finish a job in 24 days, while 'B' is 25% less efficient than 'A.' If they take turns working, beginning with 'A,' how many days will it take for...