Start learning 50% faster. Sign in now
Get Started with ixamBee
Start learning 50% faster. Sign in nowThe correct answer is A
A and B together can complete a piece of work in 35 days while A alone can complete 50% of the work in 20 days. Find the time taken by B to complete 12....
A can finish a piece of the work in 16 days and B can finish it in 12 days. They worked together for 4 days and then A left. B finished the remaining wo...
A and B can do a work in 21 days, A is (7/4) times as efficient as B. In how many days, A alone can complete the (100/3)% of the work?
Working together A and B can do a job in 40 days, B and C in 36 days and all three together in 24 days. In how many days can B alone do the job?
In a 200 m race, P beats Q by 35 m or 7 seconds. What is P's time over the course?
P and Q can complete a project in 15 days and 10 days, respectively. They started doing the work together, but after 2 days, Q had to leave and P alone...
A’ and ‘B’ together can complete a work in 8 days, while ‘B’ and ‘C’ together can complete the work in 12 days...
The diameters of three inlet pipes of a cistern are 1.5 cm, 2 cm and 2.5 cm respectively. The pipe with the maximum diameter can alone fill up the ciste...
A can complete a certain work in 30 days. B is 25% more efficient than A and C is 20% more efficient than B. They all worked together for 3 days. B alon...
'K' can do 3/4th of a work in 6 days and 'J' can do 2/5th of the same work in 4 days. How long (in days) will they take, if they w...