    Question

    A is twice as efficient as B at completing a task, and

    together they can finish the task in 20 days. How many days would A alone take to complete the task?
    A 34 days Correct Answer Incorrect Answer
    B 30 days Correct Answer Incorrect Answer
    C 28 days Correct Answer Incorrect Answer
    D 32 days Correct Answer Incorrect Answer

    Solution

    A is twice as efficient as B, and together they can complete a task in 20 days. ┬а Let B's work rate be x. ┬а A's work rate is 2x. ┬а Combined work rate of A and B: 2x + x = 3x. ┬а Together they complete the task in 20 days: 3x = 20 ┬а ┬а x = 1 /60 ┬а A's work rate is 2x=2├Ч 1 /60 =1 /30 =30days