๐Ÿ“ข Too many exams? Donโ€™t know which one suits you best? Book Your Free Expert ๐Ÿ‘‰ call Now!

  • google app store apple app store
  • โœ–

      Question

      P can complete a work in 12 days working 8 hours a day,

      Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?
      A 5(5/11) Correct Answer Incorrect Answer
      B 5(6/11) Correct Answer Incorrect Answer
      C 6(5/11) Correct Answer Incorrect Answer
      D 6(6/11) Correct Answer Incorrect Answer

      Solution

      ATQ,

      P's rate: P completes the work in 96 hours (12 days ร— 8 hours/day). So, Pโ€™s work rate is 1/96 of the work per hour. Q's rate: Q completes the work in 80 hours (8 days ร— 10 hours/day). So, Qโ€™s work rate is 1/80 of the work per hour. When they work together, their combined work rate is:

      Thus, together they complete 11/480 of the work per hour. The time taken to complete the work is:

      Since they work 8 hours a day, the number of days they will take is:

      ย 

      orย  5(5/11)ย 

      Practice Next
      ask-question