Question
Rohit and Mohit can do a piece of work in 4 days. While Ram and Shyam can do the same work in 12 days. In how many days will Rohit, Mohit, Ram and Shyam do it together?
More Previous year papers Questions
- The value of (1 + (1 – 2)–1 + 2 – (1 – 2)–2)2 is:
- At a certain time in a park, the number of heads and the number of legs of monkeys and human visitors were counted, and it was found that there were 54 hea...
- The average of 30 numbers is 55. The average of the first 15 numbers is 51 and the average of the last 12 numbers is 56. What is the average of 68, 74 and ...
- A shopkeeper decides to raise the marked price of an article by 40%. How much percentage discount should he allow to be able to sell the article at the ori...
- Two trains of lengths 310 m and 340 m, respectively, are 285 m apart. They start moving towards each other on parallel tracks, at the speeds of 151 km/h an...
- What will be the difference between the total surface area and the curved surface area of a hemisphere having 4 cm diameter?
- The marked price of an article is Rs 5000. But due to a special festive offer a certain percent of discount is declared. Mr. X availed this opportunity and...
- Find the simple interest (in ₹) on ₹3500 as a sum borrowed at 6% per year rate of interest for 2 years.
- A cylindrical bucket of radius 42 cm and height 48 cm is full of water. The water is emptied into a rectangular rub of length x cm and breath 84 cm. If the...
- The radius of the base of a conical tent is 9 m and its height is 12 m, find the cost of the material needed to make it if it costs ₹100 per π m².
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)