Question
A sum was invested at 12.5% simple interest for 3 years.
If the same sum was invested at 4.16% more for the same period, then it would have fetched Rs.120 more. Find the amount invested. (in Rs.)Solution
SI @ 12.5% p.a. = (12.5 × 3 × P)/100 = 0.375P SI @ (12.5% + 4.16% = 16.66%) = (16.66 × 3 × P)/100 = 0.4998P ATQ, 0.4998P - 0.375P = 120 0.1248P = 120 P = 961 so, according to option 960 is the closest answer.
Ravi and Rekha, alone can complete a work in 25 days and 50 days, respectively. They started the work together and left after 10 days such that the rema...
A alone can finish a piece of work in 10 days and B alone can finish it in 15 days. They work together for 3 days and the remaining work is finished by ...
P, Q & R can finish a work in 10 days, 15 days, and 20 days, respectively, working alone. P and Q work on the first day, P and R work on the second day,...
(x + 6) workers complete 40% of a job in 8 days by working 5 hours/day. The remaining work is done by (x + 2) workers in 16 days working 5 hours/day. Fi...
Amin, Basha and Cheez can do a piece of work in 90, 40 and 12 days respectively. But they decide. That a single person will work in a day and receive Rs...
138 unit of work can be completed by P alone in 23 days. P started working alone and joined by Q after 11 days such that they completed the remaining wo...
- Two workers, A and B, can finish a task in 36 days and 48 days respectively, working alone. How many days will they take to complete the work together?
- Pipes X and Y can fill a tank in 45 minutes and 60 minutes respectively. Another pipe Z can empty the tank in 1 hour 30 minutes. If X and Z are opened firs...
8 men working 6 hours a day can complete a piece of work in 6 days. If efficiency of each woman is 20% more than that of each man, then how many women w...
- Alok finishes 60% of a project in 30 days, while Neha finishes 20% of the same in 15 days. Alok worked for 25 days and then stopped. Find the time taken by...