- A alone can complete a work in 18 days and B alone in 14 days. Starting with A, they work on alternate days. The total work will be completed in:
- Mayank, Deepak and Pawan, each of them working alone can complete a work in 5, 10 and 15 days respectively. If all three of them work together to complete ...
- A shopkeeper bought one item in Rs.500, and sold it in Rs.400. Find the percentage of the loss. (% In)
- A set of data presented in the form of a frequency distribution table with class intervals and their respective frequencies had a mode of 48.5. The lower b...
- The ratio of alcohol and water in solutions A and B is 3 : 5 and 5 : 7, respectively. Two litres of A is mixed with 5 litres of B and 3 litres of alcohol i...
- Three rectangular fields having areas of 70 m², 84 m², and 112 m² are to be divided into identical rectangular flower beds, each having a length of 7 m. Fi...
- Divide 2310 people into three parties such that half of the number in the first party, one-third of the number in the second party and one-sixth of the num...
- The cost price of an article is 76% of its marked price. Find the gain percentage after allowing a discount of 5%.
- A can paint a house in 45 days and B can do it in 15 days. Along with C, they did the job in 5 days only. Then, C alone can do the job in how many days?
- A pyramid has an equilateral triangle as its base, of which each side is 8 cm. Its slant edge is 24 cm. The whole surface area of the pyramid (in cm2) is:
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)