      Question

      Twenty persons take 15 days to complete a certain work

      working 8 hours a day. To complete the same work in 4 days, working 10 hours a day, the number of persons required is:
      A 75 Correct Answer Incorrect Answer
      B 60 Correct Answer Incorrect Answer
      C 80 Correct Answer Incorrect Answer
      D 55 Correct Answer Incorrect Answer

      Solution

      The correct answer is B