    Question

    If a mam completes 3/7 work in 6 days, then how many

    more days will he require of completing the remaining work?
    A 8 Correct Answer Incorrect Answer
    B 14 Correct Answer Incorrect Answer
    C 9 Correct Answer Incorrect Answer
    D 7 Correct Answer Incorrect Answer

    Solution

    The correct answer is A