Question

Machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours. All the machines are started at 9
A.M. while machine P is closed at 11
A.M. and the remaining two machines complete work. Approximately at what time will the work (to print one lakh books) be finished?

A 11:30 A.M.
B 12 noon
C 12:30 P.M
D 1:00 P.M.