πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!


    Question

    β€˜P’ and β€˜Q’ can do a piece of work in 12 days

    and 18 days, respectively. β€˜P’ started working alone and was replaced by β€˜Q’ after 4 days. In how many days can β€˜Q’ complete the remaining amount of work alone?
    A 8 days Correct Answer Incorrect Answer
    B 10 days Correct Answer Incorrect Answer
    C 12 days Correct Answer Incorrect Answer
    D 14 days Correct Answer Incorrect Answer

    Solution

    Let the total work be 36 units (LCM of 12 and 18) Efficiency of β€˜P’ = 36/12 = 3 units/day Efficiency of β€˜Q’ = 36/18 = 2 units/day Let the number of days taken by β€˜Q’ to finish the remaining amount of work be β€˜x’ ATQ, (3 Γ— 4) + 2x = 36 Or, 2x = 36 – 12 Or, 2x = 24 Or, x = 24/2 = 12 Therefore, time taken by β€˜Q’ to complete the remaining work alone = 12 days

    Practice Next

    Relevant for Exams:

    ask-question