Question
βPβ and βQβ can do a piece of work in 12 days
and 18 days, respectively. βPβ started working alone and was replaced by βQβ after 4 days. In how many days can βQβ complete the remaining amount of work alone?Solution
Let the total work be 36 units (LCM of 12 and 18) Efficiency of βPβ = 36/12 = 3 units/day Efficiency of βQβ = 36/18 = 2 units/day Let the number of days taken by βQβ to finish the remaining amount of work be βxβ ATQ, (3 Γ 4) + 2x = 36 Or, 2x = 36 β 12 Or, 2x = 24 Or, x = 24/2 = 12 Therefore, time taken by βQβ to complete the remaining work alone = 12 days
If the following interchanges are made in signs, then what would be the value of the following expression?
48 X 63 + 2 Γ· 9 - 35Β
Interch...
A shopkeeper sells rice in such a way that the selling price of 950 gm is the same as the cost price of one kilogram. Find his gain percent.
Select the correct combination of mathematical signs that can sequentially replace the β@β sign and balance the following equation.
14@6@8@3@...
Select the correct combination of mathematical signs that can sequentially replace β*β sign and balance the equation given below.
42 * 18 ...
Which two signs need to be interchanged to make the following equation correct?
75 β 18 Γ 80 Γ· 16 + 40 = 125
Which two digits and signs can be interchanged so as to balance the given equation?
328 - 82 + 120 X 6 Γ· 41 = 646
By interchanging the given two numbers (not digits), which of the following equations will be correct?
24 and 15
I. 113 + 24 - 17 X 1...
IfΒ β + β means ' Γ ', β β β means ' Γ· ' , βΓβ means '+' and βΓ·β means 'β', Then compute the value of the expression: 54 β 9 ...
If β+β means βminusβ, βΓβ means βdivided byβ, βΓ·β means βplusβ, and β-β means then βmultiplied byβ
250 Γ 10 οΏ½...
Which two signs should be interchanged to make the given equation correct?
15 Γ· 6 - 10 x 5 + 11 = 99