Question
A can do a piece of work in 12 days, while B
alone can do it in 18 days. They work together for 6 days and the rest of the work is completed by C in 4 days. If they get Rs. 720 for the whole work, how should they divide the money?Solution
Work done by A and B in 6 days = (1/12 + 1/18) × 6 = 5/6 Work remaining = 1 - 5/6 = 1/6 ∴ C alone can do the work in 6 × 4= 24 days Ratio of their share work = 6/12 : 6/18 : 4/24 = 3:2:1 Share of A’s wages = 3/6 × 720 = Rs. 360 Share of B’s wages = 2/6 × 720 = Rs. 240 Share of C’s wages = 1/6 × 720 = Rs. 120 Alternate Method: A B Time taken 12 18 Total work = LCM 36 units 3 : 2 ATQ, A+B's work in 6 days = (3+2)`xx` 6 = 30 units So remainning work = 36 - 30 = 6units which is completed by C alone in 4days So C's 1 day work = 6/(4)=1.5units Hence ratio of work done of A, B & C = 3 `xx` 6 : 2 `xx` 6 : 6 = 18 : 12:6 = 3:2:1
Which of the following statements is/are incorrect?
Who left Google to spread awareness towards the rising threats of AI to society?
Which regulatory body has approved the stake acquisition in climate technologies' business of Emerson Electric Co by BCP Emerald Aggregator LP?
The Olympic Winter Games 2026 would be played in_______.
According to the latest employment-unemployment indicators report released by the National Statistical Office (NSO), what was India's unemployment rate ...
Which satellite was recently re-entered into Earth's atmosphere by ISRO (Indian Space Research Organisation)?
Which Indian state has signed a Memorandum of Association with La Liga to establish a football academy and promote the sport?
Which type of rock is most likely to contain fossils?
The term Virovore is sometimes mentioned in News. Which of the following correctly define the given term:
What is the capacity of India’s first CO2 to methanol pilot plant being constructed in Pune?