Question
A can do a piece of work in 12 days, while B
alone can do it in 18 days. They work together for 6 days and the rest of the work is completed by C in 4 days. If they get Rs. 720 for the whole work, how should they divide the money?Solution
Work done by A and B in 6 days = (1/12 + 1/18) × 6 = 5/6 Work remaining = 1 - 5/6 = 1/6 ∴ C alone can do the work in 6 × 4= 24 days Ratio of their share work = 6/12 : 6/18 : 4/24 = 3:2:1 Share of A’s wages = 3/6 × 720 = Rs. 360 Share of B’s wages = 2/6 × 720 = Rs. 240 Share of C’s wages = 1/6 × 720 = Rs. 120 Alternate Method: A B Time taken 12 18 Total work = LCM 36 units 3 : 2 ATQ, A+B's work in 6 days = (3+2)`xx` 6 = 30 units So remainning work = 36 - 30 = 6units which is completed by C alone in 4days So C's 1 day work = 6/(4)=1.5units Hence ratio of work done of A, B & C = 3 `xx` 6 : 2 `xx` 6 : 6 = 18 : 12:6 = 3:2:1
Pusa Jai Kisan (Bio-902) is a variety of
In insects middle segment of thorax is known as ______:
Which of the following wheat sp. occupies maximum area in India?Â
Which of the following plants is an example of a biennial?
The analytical condition where a farmer seeks to produce a given level of output using the least costly input combination, given input prices, is known ...
Which is an illustration of relay cropping?
Landraces are very good sources of genes for:
At what PF wilting percentage arrives
In the context of rice physiology, which growth stage is most critical for water management and has the greatest influence on yield formation?
The term ‘Green Revolution’ was coined by ?