Question
A can do a piece of work in 12 days, while B
alone can do it in 18 days. They work together for 6 days and the rest of the work is completed by C in 4 days. If they get Rs. 720 for the whole work, how should they divide the money?Solution
Work done by A and B in 6 days = (1/12 + 1/18) × 6 = 5/6 Work remaining = 1 - 5/6 = 1/6 ∴ C alone can do the work in 6 × 4= 24 days Ratio of their share work = 6/12 : 6/18 : 4/24 = 3:2:1 Share of A’s wages = 3/6 × 720 = Rs. 360 Share of B’s wages = 2/6 × 720 = Rs. 240 Share of C’s wages = 1/6 × 720 = Rs. 120 Alternate Method: A B Time taken 12 18 Total work = LCM 36 units 3 : 2 ATQ, A+B's work in 6 days = (3+2)`xx` 6 = 30 units So remainning work = 36 - 30 = 6units which is completed by C alone in 4days So C's 1 day work = 6/(4)=1.5units Hence ratio of work done of A, B & C = 3 `xx` 6 : 2 `xx` 6 : 6 = 18 : 12:6 = 3:2:1
Who was conferred the Padma Bhushan for contributions to journalism in 2025?Â
What is the expected annual energy output of the Heo Hydro Electric Project?
Which tennis legend won the 2025 Princess of Asturias Award for Sports?
Which space tech firm will launch India’s first AI laboratory in space aboard PSLV C60?
Where was India’s first cooperative multi-feed Compressed Biogas (CBG) plant inaugurated in October 2025?Â
What is the deployment timeline mandated by SEBI for funds raised through New Fund Offers (NFOs)?
Which Indian bank became the first to launch Central Bank Digital Currency (CBDC) retail transactions via UPI QR codes?
Which mission was launched by ISRO on July 14, 2024?
- What milestone did India achieve in the global arms trade as per the SIPRI report 2025?
Which newly discovered gecko species in Assam indicates biogeographic links with Sri Lanka?Â