Question
A person marks his goods 40% above the cost price. He
sold 30% of goods at marked price, 60% of the remaining at a discount of 20% and remaining at 40% discount .What is 60% of his overall gain percent?Solution
Let there are 100 goods (articles) cost of each article be Rs. 1 Total cost of 100 articles = Rs. 100 MP of 100 articles = 100 Γ 140/100 = Rs. 140 30% of 100 = 30 Remaining = 100 β 30 = 70 60% of 70 = 42 Rest = 100 β 30 β 42 = 28 Total SP of 100 articles 30 Γ (140/100) + 42 Γ (140/100) Γ (80/100) + 28 Γ (140/100) Γ (60/100) β 42 + 47.04 + 23.52 β 112.56 Profit = 112.56 β 100 = 12.56 Profit percentage = 12.56/100 Γ 100 = 12.56%
βAβ alone can complete a work in 50 hours. βAβ started the work alone and left after working on it for 10 hours. If βBβ completed the rest o...
40 tailors can stitch a batch of dresses in 30 days. If 20 tailors started the job and after 15 days βuβ more tailors joined them such that the rema...
A can complete a piece of work in 10 days and B can complete it in 15 days. They start working together, but B leaves after 3 days. In how many more day...
- An organization engaged 16 workers to complete a task in 24 days. After 9 days, 6 workers had to leave unexpectedly. How many additional days will it now t...
A contractor planned to complete a project in 5 days by employing βaβ workers. But every day exactly 15 workers were absent. As a result, the work g...
Arjun and Sameer can complete a job in 20 days and 25 days respectively. When Arjun, Sameer, and Nikhil work together, they finish it inΒ
M, N and O can complete a task in βtβ, 100, and βt + 20β days respectively. All three started together, but after 15 days, N dropped out. Then, ...
(x + 7) workers finish 60% of a job in 9 days working 4 hours/day. The remaining work is done by (x + 3) workers in 12 days working 3 hours/day. Find x.
A work can be completed by βAβ and βBβ, alone in 10 days and 12 days, respectively. Find the number of days taken by βCβ to complete the sam...
A piece of work consists of 360 identical units. A can do (x + 4) units per day and B can do (x β 2) units per day. They work together for 9 days and ...