Question
The ratio of quantity of milk to that of water in a 48
litre of mixture is 3:1. If 'x' litres of mixture is replaced by same quantity of water, then the ratio of quantity of milk and water becomes 2:1, respectively. Find the value of 'x'.Solution
Let the quantity of milk and water in the mixture be '3a' litres and 'a' litres, respectively. So, total quantity of milk in the mixture = (3a/4a) × 48 = 36 litres total quantity of water in the mixture = (a/4a) × 48 = 12 litres Let the total quantity of water taken out be 'b' litres. Then, total quantity of milk taken out = (x - b) litres ATQ, (x - b):b = 3:1 Or, x - b = 3b Or, x = 4b....(i) Now, {36 - (4b - b)}:(12 - b + 4b) = 2:1 Or, 36 - 3b = 24 + 6b Or, 9b = 12 So, 'b' = 4/3 From equation (i) 'x' = 4b = 4 × 4/3 = 5.33
X, Y and E can do piece of work in 24, 30 and 40 days respectively. All three began to work together but X and Y left 6 and 8 days respectively before c...
'X' and 'Y' can complete a certain job together in 36 days. They worked together for 20 days, after which 'X' left, and 'Y' completed the remaining work...
Working 10 hours a day, Jagan can complete a work in 12 days while working 8 hours a day, Magan can complete the same work in 9 days. If Jagan and Magan...
- Person A is twice as efficient as Person B. Person B can complete a certain task in 32 days, while Person C takes 4 days more than Person A to finish the s...
- 50% of the work done by Meena in 2 days is equal to 25% of the work done by Lata in 5 days. If Meena can complete the job alone in 10 days, then how long w...
A and B can complete a work together in 20 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed by B alo...
A can complete a work in 20 days. B takes 10 days less than A to complete the same work. In how many days can both of them together complete 90% of the ...
Q can do a work in 15 days and R can do the two-third work done by P and Q together in a day. If R completes the work in 18 days, how many days will it ...
Rohan can finish a task alone in 24 days. Shreya can do 50% of the same task alone in 12 days. If Shreya and Tanya work together, they can complete 60% ...
A alone can complete 40% of a work in 18 days while B takes 15 days more than A to complete it. If B and C together can complete the work in 20 days, th...