If all five workers start working together, how many
days will they take to complete the entire 500 units of work? Direction: Five workers – A, B, C, D, and E – are working on a construction project to complete 500 units of work. Each worker works different numbers of hours per day and has varying work efficiencies, which are calculated as the number of units completed per hour. The following table shows the daily working hours and the efficiency (units per hour) for each worker:Solution
Total work done by A in 1 day = 8 × 2 = 16 units. Total work done by B in 1 day = 6 × 3 = 18 units. Total work done by C in 1 day = 5 × 4 = 20 units. Total work done by D in 1 day = 7 × 2.5 = 17.5 units. Total work done by E in 1 day = 9 × 1.8 = 16.2 units. Total units per day by all workers = 16 + 18 + 20 + 17.5 + 16.2 = 87.7 units/day. Days required = 500 ÷ 87.7 ≈ 5.7 days.
Which weed classification involves plants that grow in wild as well as cultivated lands?
Which of the following disease occurs due to deficiency of zinc in rice?
Which category includes crops like coriander, cumin, and carrot based on taxonomy?
Ooze test is used for the detection of ___
The yellow vein mosaic of okra is majorly transmitted by ____
For the farmers, ………………………………. Soil structure is favourable for plant growth.
...Identify the cropping practice adopted in regions prone to climatic uncertainties, involving the cultivation of crops without definite row arrangements.
Genes governing traits showing cytoplasmic inheritance are located outside the nucleus and in the cytoplasm, they are referred to as _________...
Which among the following is Photoblastic Seed?
Match Lis I with List II
Choose the correct answer f...