Question
Workers C and D work together for 10 days. Calculate how
many units they will complete in this period. Direction: Five workers – A, B, C, D, and E – are working on a construction project to complete 500 units of work. Each worker works different numbers of hours per day and has varying work efficiencies, which are calculated as the number of units completed per hour. The following table shows the daily working hours and the efficiency (units per hour) for each worker:Solution
Total work done by C in 10 days = 10 × 5 × 4 = 200 units. Total work done by D in 10 days = 10 × 7 × 2.5 = 175 units. Total work by C and D = 200 + 175 = 375 units.
- In each sentence below four words have been printed in bold which are numbered (1), (2), (3) and (4) One of these words may be misspelt or inappropriate in...
Choose the correctly spelt word.
In each question below, four words that are numbered a, b, c, and d have been printed of which one may be wrongly spelt. The number of that word is the ...
Choose the word with correct spelling.
(a) Tariff (b) Tarriff
(c) Tarif (d) Tarrif
Choose the correctly spelt word.
In each question below, a sentence is given with a part of it printed in bold type. That part may contain a grammatical error. Each sentence is followe...
Select the Incorrectly spelt word.
- Identify the INCORRECTLY spelt word in the following sentence and select its correct spelling from the given options.
The committee appreciated her... In the following question, four words are given, out of which only one word is correctly spelt. Find the correctly spelt word.