Question
Aman, Sam and Kiran started working together but after 8
days Kiran left the job and 5 days before the completion of the work Sam also left then, In how many days the whole work gets completed? Suppose five friends Ritu, Mohani, Aman, Sam and Kiran are appoints to complete a certain piece of work. Ram and Mohani together can complete a work in 24 days. Mohani and Aman together can complete 50% of the work in 15 days. Aman and Sam together can complete the work in 24 days. Ritu and Kiran together can complete 16.66% of the work in 6 days. Sam and Kiran together can complete the work in 20 days.Solution
ATQ, we can say that Efficiency of, Ram = r, Mohani = m, Aman = a, Sam = s, Kiran = k (r + m) Γ 24 = (m + a) Γ 30 = (a + s) Γ 24 = (r + k) Γ 36 = (s + e) Γ 20 = 360 r + m = 15, m + a = 12, a + s = 15, r + k = 10, s + k = 18 (m + a) + (a + d) β (r + m) β (s + k) + (r + k) = 12 + 15 β 15 β 18 + 10 2a = 4 a = 2, m = 10, r = 5, s = 13, k = 5. ATQ, Let work will be completed in w days 2 Γ w + 13 Γ (w β 5) + 5 Γ 8 = 360 2w + 13x β 65 + 40 = 360 15w = 360 + 25 = 385 w = 77/3 days
Armaan and Bhanu working together can finish a certain task in 90 days, and Bhanu collaborating with Chintu can complete the same task in 70 days. If Ar...
Two individuals, P and Q, can complete a task in (x + 6) days and (x + 3) days, respectively. Another individual, S, is capable of completing 25% of the...
The efficiency of A, B, C, D are in the ratio of 6 : 5 : 4 : 3. If A and C can do a work together in 6 days. Then How much days B and D will take to com...
'A' requires 16 more days to finish a task compared to 'B'. When 'A' and 'B' collaborate, they complete the task in 9 days fewer than 'B' would need to ...
When working alone, Ansh takes 12 more days than time taken by Ansh and Balu together to finish certain work. If Ansh is 50% more efficient than Balu, t...
Virat can do a piece of work in 26 days and Sachin can do the same work in 39 days. If Virat works for 5 days and got Rs. 3000, and the remaining work w...
A contractor undertook to make 20 km of roadway in 48 weeks. In 28 weeks, 8 km was completed by 120 men working 12 hours a day. The men then agreed to w...
40 men can complete a piece of work in 48 days. βxβ men started the work and after 33 days 64 more men joined them so that whole work was finished i...
A group of 21 boys, each working 6 hours a day, complete a school project in 15 days. How many days will it take for 18 boys, wor...
- Priya can solve 30 questions in 1.5 hours. If she decreased her efficiency by 25%, then how much time would she take to solve the same number of questions?