Question
If Chinky worked for whole time and Arjun & Bheem work alternatively with Chinky, then what will be the minimum number of required days to complete the work.
The ratio of number of days taken by Arjun and Bheem to complete a work individually is 7:8 and the ratio of number of days taken by Bheem and Chinky to complete a work individually is 6:7 and the ratio of number of days taken by Chinky, Danny, Elli and Finn to complete a work individually is 28 : 30 : 35 : 40. Arjun takes 21 days to complete a work individually.
More Databased Ratio Questions
- Company X considered the price of watch of type II as Rs. 1 lac and placed an order for 4 watches of type III, 2 watches of type II and 1 watch of type I. ...
- How much percent more does a type III watch cost compared to a type II watch?
- Danny & Elli together complete work ‘p’ in (z – (67/52)) days, while Danny & Finn together can complete the work ‘q’ in ‘z’ days. If work ‘Q’ is 20% more t...
- If both the companies X and Y placed an order for 3 watches of type I, 4 watches of type III and 2 watches of type II, what is the difference between the a...
- Arjun works for ‘x’ days and he complete 20% of work. while remaining work is completed by Bheem & Chinky together in (x + 190/13) days, then What will be ...
- Company Y placed an order considering the rate of type III watch as Rs. 1.5 Lakhs. What amount would the company have to pay for 3 watches of type IV and 2...
- Company Z considered the price of type II watch as Rs. 50,000. The company placed an order for 2 watches of each type and paid an advance amount of Rs. 2 L...
- Arjun & Chinky together start work and do it for 10 days and rest work is completed by Danny & ‘X’ together in 4 days. Then, in how many days ‘X’ alone can...