Question
Find the ratio of number of surgical mask to the number
of N95 masks sold on Tuesday. Answer the following questions based on the information given below: A shopkeeper sold two types of masks i.e. surgical and N95. Number of surgical masks sold on Monday is [P] which is 60 more than the number of N95 masks sold on same day. Number of surgical masks sold on Tuesday is [Q] which is 20% less than that on Monday and number of N95 masks sold on Tuesday is [R]. Total masks sold on Tuesday is 28% less than that on Monday while total masks sold on Tuesday is 432. Number of N95 masks sold on Wednesday is [S] which is 15% more than number of surgical masks sold on same day. Ratio of total masks sold on Monday to Wednesday is 60:43.Solution
Total number of masks sold on Monday = 432/0.72 = 600 Number of N95 masks sold on Monday = (600 – 60)/2 = 270 Number of surgical masks sold on Monday [P] = (600 – 270) = 330 Total number of masks sold on Tuesday = 432 Number of surgical masks sold on Tuesday [Q] = (80/100) × 330 = 264 Number of N95 masks sold on Tuesday [R] = 432 – 264 = 168 Total number of masks sold on Wednesday = (600/60) × 43 = 430 Number of surgical masks sold on Wednesday = (20/43) × 43 = 200 Number of N95 masks sold on Wednesday [S] = 430 - 200 = 230 Required ratio = 264 : 168 = 11:7
A man, a woman and a boy can do a work in 3, 2, 6 days respectively. How many children were required with 1 man and 1 woman to complete the same work in...
Arun and Bala, alone can complete a work in 20 days and 30 days, respectively. They started the work together and left after 8 days such that the remai...
Sachin can complete a job in 15 days. Ankit alone can complete the same job in 10 days. Sachin works for 9 days and then the remaining job is completed ...
'A' and 'B' can do a piece of work together in 30 days. They worked together for 18 days, and then left the work. The remaining job was finished by 'C' ...
- Aman and Rohan can finish a job alone in 12 days and 30 days respectively. Aman began the task alone. After how many days should Rohan join him so that the...
A can do a piece of work in 40 days. A is 25% more eicient than B. In how many days the work gets completed when both of them work together?
A can complete a piece of work in 10 days and B can complete it in 15 days. They start working together, but B leaves after 3 days. In how many more day...
- M and N together complete a work in 10 days, while N alone does it in 16 days. If the efficiency of M to O is in the ratio 5:6, what is the ratio of effici...
12 man can make a wall in 5 days. How many men required to complete the same work in 6 days ?
βAβ and βBβ can complete a certain work in 16 days and 32 days, respectively. They started working together and worked till completion of the wo...