Question
P and Q can complete a work in 24 days and 36 days, respectively. P, Q and R together can complete the work in 12 days. If R get a total wage of Rs. 6120 to complete the work alone, then find the per day wage of R.
More Boats and streams Questions
- Find the total distance covered by boat in each upstream and downstream in 6 hours if the speed of boat in still water and speed of current is 18 km/h and ...
- A boat takes 3 hours 45 minutes to cover 67.5 km in downstream. The ratio of the speed of the boat in still water to the speed of the stream is 5:1. Find t...
- Calculate the speed of a boat in still water if it travels 176 km downstream in 11 hours and returns 144 km upstream in 18 hours.
- The current age ratio of Aman and Arjun is 3:4, respectively. After 6 years, their ages will be in the ratio 4:5. What is Aman’s present age?
- The speed of a boat in still water is three times the speed of the boat upstream. If the boat takes 30 minutes to cover 27 km downstream, then find the spe...
- A boat covers a distance of 240 km downstream in 8 hours. If the ratio of upstream speed to downstream speed of the boat is 2:5, then find the distance tra...
- A boat can cover 150 km in downstream in 15 hours and 130 km in upstream in 13 hours. Find the distance travelled by the boat in still water in 5 hours.
- "A boat takes 60 seconds to travel ______ metres downstream and 40 seconds to travel ______ metres upstream in the same river. The speed of the stream is _...
- A boat covers 24 km upstream in 4 hours and 42 km downstream in 3 hours. What is the speed of the stream?
- The speed of a boat in still water is twice the speed of the current. The difference between downstream and upstream speeds is 16 km/h. If the boat spends ...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt