Question

Using the Basic COCOMO model for an organic-type project, with a = 2.4 and b = 1.05, what is the approximate effort required for an estimated project size of 50 KLOC?

A ≈ 146 person-months
B ≈ 60 person-months
C ≈ 120 person-months
D ≈ 100 person-months
E ≈ 175 person-months