Question

Given processes with arrival times and burst times — P1(0,5), P2(1,3), P3(2,8), P4(3,6) — what is the average waiting time using Shortest Job First (SJ

  • F preemptive (Shortest Remaining Time First) scheduling?
A 5.0
B 6.5
C 4.75
D 5.5
E 7.0