'A' can complete a certain task in 60 days, while 'B' can do the same in 45 days. 'A' starts the task and works alone for 18 days, after which 'B' joins...
A group of 'x' men can finish a job in 46 days. If 8 additional men had joined the group, they could have completed the same job 16 days earlier. Assumi...
A pipe can fill a tank in 12 hours, while a second pipe can empty it in 18 hours. If both pipes are opened at the same time, how long will it take to fi...
‘A’ can do a piece of work in 15 days. ‘B’ can do 70% of the same work in 20 days. If they work together for the entire time and...
A team of 40 men is assigned to finish a project within 24 days. They began the task simultaneously. To complete the project 6 days ahead of the planned...
Work Efficiency of Raghav and Vaibhav are in the ratio of 12:14. Both of them worked together and finished the work in 9 days. In how many days, the tot...
Worker 'A' takes 16 more days than the combined time taken by workers 'A' and 'B' together to complete a certain job. If worker 'B' alone can finish the...
A work can be completed by ‘A’ and ‘B’, alone in 18 days and 10 days, respectively. Find the number of days taken by ‘C’ to complete the sam...
‘A’ alone can do some work in 13 days. ‘B’ and ‘C’ together can do the same work in 18 days. If ‘B’ is half as efficient as ‘A’, the...