Question
What is the overall capacity of the Srinagar
Hydroelectric Project?Solution
Srinagar Project Dam RiverAlakhnanda LocationVishnuprayag Its installed capacity is 330 MW (4x82.5 MW).
Ratio of the work done by P, Q and R in one day is 5:4:8 respectively. They all together can complete the work in 40 days. Q and R worked on it for 20 d...
'A' requires 16 more days to finish a task compared to 'B'. When 'A' and 'B' collaborate, they complete the task in 9 days fewer than 'B' would need to ...
45 men can complete 3/5 part of a work in 8 days working 9 hours a day. How many women can complete rest of the work if they work for 6 hours a day for ...
βAβ and βBβ together can complete a work in 10 days, while βBβ and βCβ together can complete the work in 20 days. If βBβ takes 8 day...
Pβs 5 days work is equal to Qβs 6 days work. If P and Q together can complete the work in 25 days then how much time Q will take to complete 80% of ...
N workers can complete a piece of work in 50 days. When 5 more workers joined, then the work got completed in 40 days, then what is the value of N?
The day efficiency of Rajeev is equal to the one-day efficiency of Divya and Vivek together. Divya is 25% more efficient than Vivek and starts with 20% ...
A can complete a piece of work in 12 days and B can complete it in 18 days. They work together for 4 days and then B leaves. In how many more days will ...
A and B together can do a work in 8 days. If A can alone do the same work in 12 days, then in how many days B alone will do the same work?
'A' and 'B' together can do a piece of work in 12 days while 'B' and 'C' together can do the same work in 15 days. 'A' started the work alone and worke...