A and B together can complete a work in 12 days, and B alone can complete it in 20 days. How many days will A take to complete the work alone?
Mike and Jenny alone can complete a task in 24 days and 40 days respectively. They aim to finish the work in 'd' days. What percentage increase in Jenny...
105 people could complete a work in 36 days. But after they worked together for 7 days their employer wanted the work should be completed in a total of ...
P, Q, R can do a piece of work in 40 days, 90 days, and 36 days, respectively. P started the work. Q joined him after 8 days. If R joined them after 9 d...
It is given that 40% of the work completed by Lokesh is equal to 30% of the work completed by Meena. If Lokesh alone can complete the entire work in 28 ...
‘A’ and ‘B’ can do a piece of work in 20 days and 40 days, respectively. If they started the work together and worked on it for 6 days, then fin...
A person can complete a work in 15 days, and another person can complete the same work in 20 days. They work together for 5 days, and then the first per...
A job is done by 15 men in 30 days and 30 women in 20 days. How many days will it take for 8 men and 12 women to finish the work?
Ravi and Manish can do a piece of work in 16 days and 20 days respectively. How long will it take to finish the work if Manish is to be replaced by Sanj...
A and B together can complete a piece of work in 25 days while A alone can complete 50% of the work in 50 days. Find the time taken by B to compl...