The correct answer is B
40 tailors can stitch a batch of dresses in 30 days. If 20 tailors started the job and after 15 days ‘u’ more tailors joined them such that the rema...
P and Q can do a piece of work in 32 and 40 days respectively. They began to work together but P leaves after sometimes and Q completed remaining work i...
A man takes 200 days to finish a work alone. If he started working alone and joined by one more man having same efficiency as of him every day from 2nd ...
A man, a woman and a boy can do a work in 4, 8, 32 days respectively. How many boysare required with 1 man and 1 woman to complete the same work in 1/4 ...
"A" can finish a task in 36 days, while "B" can complete it in 45 days. Both start working on the task together, but "A" stops working after "x" days. ...
Avinash is twice as good as Bhuvanesh and together they can finish a job in 50 days. Bhuvanesh will finish the work alone in how many days?
'X' and 'Y' can complete a certain job together in 36 days. They worked together for 20 days, after which 'X' left, and 'Y' completed the remaining work...
P’s 5 days work is equal to Q’s 7 days work. If P and Q together can complete the work in 20 days then how much time Q will take to complete 75% of ...
Akhil and Nikhil together can complete a work in 10 days while Nikhil alone takes 20 days to complete 40% of the work. If the efficiency of Sachin is 25...
Ram and Shyam are partners in completing a project. Ram can finish the project in 42 days, while Shyam can complete it in 54 days. Both began the projec...