The correct answer is B
A can complete a task 40% more efficiently in 25 days, whereas B, with a 25% efficiency boost, can finish the same task in 21 days. They collaborated at...
Amrita, working alone, can accomplish her sales target in 15 days, while Varshita, working alone, takes ____ days to complete her sales target. If they ...
If 24 persons can finish 50% of work in 12 days in how many days 48 person can finish the complete work?
Find the value of "w" if Armaan can complete a Sales target in (w + 20) days, Malik can complete it in (w + 44) days, and when they work together, they ...
The efficiency of A is half than that of B and C together. The ratio of the efficiency of B and C is 5 : 4. A, B and C together can do this work in 12 d...
'C' can complete a work in 18 days whereas 'D' can do the same work in 30 days.They started working together but 'C' worked with 60% of his efficiency w...
X can build a wall in 15 days, Y can build same wall in 25 days and Z can destroy the same wall in 30 days. If X & Y worked together for P days after th...
A certain number of men, represented as 'm', can finish a task in 40 days. However, if there were 15 additional men, the same task would be completed in...
Anita is 1100% more efficient than Veena. If Veena can do (1/24)th part of work in six days, then Anita alone can complete the work in_______days. If An...
'A' and 'B' alone can complete a work in 9 days and 18 days, respectively. Find the time taken by them to complete the work if they work on alternate da...