      Question

      If 25 people working 15 hours a day can complete 5 units

      of work in 8 days, how many days would be required by 12 persons to complete 10 units of work, working 20 hours a day?
      A 20 days Correct Answer Incorrect Answer
      B 25 days Correct Answer Incorrect Answer
      C 22 days Correct Answer Incorrect Answer
      D 24 days Correct Answer Incorrect Answer

      Solution

      The correct answer is B