If 25 people working 15 hours a day can complete 5 units
of work in 8 days, how many days would be required by 12 persons to complete 10 units of work, working 20 hours a day?Solution
The correct answer is B
The Effective Revenue Deficit excludes which of the following?
Which Mobile app has been launched by DAY-NRLM for use as an effective platform for marketing of the products made by women cf self-help groups.
Which of the following Statement about the SMILE Scheme is True?
Which of the following Statements about the SDGs is/are True?
I- The Sustainable Development Goals are a set of seventeen pointer targets that...
In which of the following ways, Infrastructure contributes to economic development?
(1) by increasing the productivity of the factors of product...
Identify the correct statement about Financial Stability & Development Council.
1.           It became operational in 2010
2.�...
What is the primary goal of the Ayushman Bhav Campaign launched by the President of India?
Consider the following Statements and choose the option with correct statements.
I- NABARD is a statutory body established in 1982 under Parliame...
As per the Economic Survey 2023-24, what was the share of the services sector in India's overall GVA at current prices in FY24?
Which of the following is referred as X in the above passage?