‘M’ is 60% more efficient than ‘N’. ‘N’ started the work alone and worked for 20 days and after that ‘N’ is replaced by ‘M’. If the ...
Some Category of workers can complete a decided project in 20 days. However, due to some unpredicted situation, 5 workers were absent. That’s why, the...
Ajay alone can complete a work in 10 days and Bittu alone can complete the same work in 15 days. Ajay starts the work alone and after three days Bittu j...
A’ and ‘B’ together can complete a work in 25 days while ‘A’ takes 30 days to complete the same work alone. If ‘C’ is 20% more efficient t...
Anmol can do a piece of work in 30 days, Bineet can complete double the work in 90 days and Chintu can do the work in 60 days. If all of them jointly ge...
Efficiency of A, and B are in the ratio of 2 : 3. If both can do a work together in 60 days. Find out how much days A will take to complete the work alone?
P’s 2 days work is equal to Q’s 5 days work. If P and Q together can complete the work in 30 days then how much time Q will take to complete 60% of ...
A work can be completed by ‘A’ and ‘B’, alone in 18 days and 10 days, respectively. Find the number of days taken by ‘C’ to complete the sam...
x men can finish a work in y days. 0.9x women can finish 1/3rd of the same work in (y - 8) days. If 0.8x women can complete 1/3rd work in 36 days. Find ...
‘A’ can do a piece of work in 12 days. ‘B’ can do 60% of the same work in 18 days. If they work together for the entire time and get paid Rs.154...