15 men can complete a work in 280 days. They started the work and after every 10 days, 15 additional men were employed. In how many days the work was completed?
More ESIC Part B Questions
- Which of the following numbers is divisible by 11?
- The apparent position of a star keeps on changing slightly because:
- The following two (2) items consist of two statements, Statement I and Statement II. Examine these two statements carefully and select the correct answer u...
- Under the Employees' State Insurance (ESI) Act, which of the following benefits is NOT provided?
- Which of the following is responsible for facilitating dialogue between employers and employees at the workplace under the Industrial Disputes Act, 1947?
- The term of office of the Comptroller and Auditor General of India is______?
- When Akbar besieged the Fort of Chitoor, who among the following defended it for four months?
- Who is known as an “Administrative Authority” under “Mines act 1952”?
- Raksha Kavach' is
- Consider the following in regards to Jugalbandi, a AI-driven multilingual chatbot: 1.It was launched by Microsoft. 2.The chatbot has been developed by AI4B...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)