📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!

  • google app store apple app store

    • Question

      Ratio of the work done by P, Q and R in one day is 7:5:9

      respectively. They all together can complete the work in 35 days. Q and R worked on it for 21 days. In how many days P will complete the remaining work.
      A 54 days Correct Answer Incorrect Answer
      B 63 days Correct Answer Incorrect Answer
      C 88 days Correct Answer Incorrect Answer
      D 78 days Correct Answer Incorrect Answer

      Solution

      Let total amount work be = 35 x 21 = 735 units Amount of work done by Q and R in 21 days = 21 x 14 = 294 units Amount of work left = 735 – 294 = 441 Required time = 441/7 = 63 days

      Practice Next

      Relevant for Exams:

      ask-question