Question
A can complete a work in 25 days. B takes 5 days less
than A to complete the same work. In how many days can both of them together complete 90% of the work together?Solution
Time taken by B to complete the work = 25 – 5 = 20 days Let the total work = 100 units Efficiency of A = 100/25 = 4 units/day Efficiency of B = 100/20 = 5 units/day Required time taken = 0.90 x 100/(4+5) = 10 days
Which body will be responsible for regulating higher education in India as per NEP 2020?
Which sub-sector of the tertiary sector has contributed the most in the year 2021-22?
The National Florence Nightingale Awards 2025 were given to recognize excellence in which field?
Who was not a member of the sub-committee constituted for the Nehru Report?
Consider the following statements with respect to ‘The Water (Prevention and Control of Pollution) Act, 1974’:
1. The Central Pollution...
Bali Jatra is the major Boita Bandana festival of a week celebrated in Cuttack from __________________ .
Consider the following events:
1. The first democratically elected communist party government formed in a State in India.
2. I...
Which organization publishes the annual World Happiness Report that ranks countries based on their levels of happiness and well-being?
Under the rule of which Viceroy did Rajagopalachari present the C.R. Formula?
Which city hosted the Global INDIAai Summit 2024?