Question
A, B, and C together can do a work alone in 10 days, 45
days, and 90 days respectively. A alone starts the work and work for 3 days and leaves the work, then B alone does the work for 8 days and leaves the work. If remaining work is done by C alone then for how many days has C worked?Solution
Total work = LCM of 10, 45 and 90 = 90 units Unit per day of A = 90/10 = 9 Unit per day of B = 90/45 = 2 Unit per day of C = 90/90 = 1 Units of work done by A in 3 days = 9 Γ 3 = 27 units Units of work done by B in 8 days = 8 Γ 2 = 16 units Remaining work = 90 β (27 + 16) = 47 units So, C has worked for 47/1 = 47 days
A and B together can complete a piece of work in 12 days while A alone can complete 70% of the work in 14 days. Find the time taken by B to compl...
1 man and 4 women can complete a work in 65 /4 days, while 3 men and 4 women can complete it in 13 /2 days. In whom many days will be 13 women complete ...
βPβ and βQβ can complete a task in 72 days, while βQβ and βRβ can finish 60% of the same task in 27 days. If βRβ is twice as efficie...
The amount of work completed by 24 men in 5 hours is equivalent to the work done by 21 women in 8 hours. A team of 33 men, working 6 hours daily, can fi...
X and Y alone can complete a work in 10 and 40 days, respectively. 50% of the work is completed by Z in 20t days, and the remaining work is completed by...
- A pipe can fill a tank in 20 hours, and B pipe can drain a tank in 15 hours. If a system of N pipes (fill pipes and drain pipes put together) can fill the ...
P and Q individually can complete the work in 22 days and 33 days respectively. If the time taken by R alone to complete the work is 1.25 times the time...
βXβ and βYβ together can complete a work in 10 days, while βYβ and βZβ together can complete the work in 8 days. If βYβ takes 12 day...
Three boys can do a work in 15 days where as 6 girls can do in 12days. What will be the time taken to complete the same work by a teacher if the efficie...
A is thrice as efficient as B and can finish a piece of work in 32 days less than B. B can finish this work in how many days?