Question
P alone can finish a piece of work ‘M’ in 9 days
while Q takes 3 days to finish it alone. P, Q and R working together can finish the work ‘N’ which is 12 times of work ‘M’ in 9 days. How long will R take to finish work ‘N’, when working alone?Solution
 Let the work ‘M’ = 9 units (LCM of 9 and 3) Efficiency of P = 9/9 = 1 units Efficiency of Q = 9/3 = 3 units Efficiency of P, Q and R = (9 × 12)/9 = 12 units per day Efficiency of R = 12 – (1 + 3) = 8 units per day Time taken by R to finish work ‘N’ = 108/8 = 13.5 days
Statements:
Some squares are circles.
No circle is a traingle.                Â
Conclusions:
Conclusions:
I. No Charger is Socket.
II. Some Plug being Battery is a Possibility
Read the given statements and conclusions carefully. Assuming that the information given in the statements is true, even if it appears to be at varianc...
- In the questions given below there are three statements followed by two conclusions I and II. You have to take the three given statements to be true even i...
Statements:
Some doors are windows.
All windows are beds.
Some beds are pillows.
All pillows are blankets.
...
In the question below some statements are given followed by two conclusions I and II. You have to take the given statements to be true even if they see...
Statements:
Only a few Plate are Cup.
Some Cup are not spoon.
Some spoon are fork.
Conclusions:
I. All Cup are Plate....
In the question below there are four statements followed by four conclusions I, II, III and IV. You have to take the four given statements to be true ...
Statements: All glasses are plates.
Some plates are bowls.
Conclusions:I. Some bowls are glasses.
II. No bowl is a glass.Â
 Statement:
Some Doctor are Nurse.
Only a few Nurse are Patient.
All Cleaner are Patient.
None of the Nurse are Accountant....