The ratio of efficiencies of X and Y for doing a certain work is 5 ∶ 9. Working together, they can complete a work in 15 days. X alone will complete 6...
A and B together can complete a piece of work in 12 days, while B and C can complete it in 15 days. A, B, and C together can complete the same work in 8...
A is twice efficient as B and B can do a piece of work in 40 days. B started the work and after a few days A joined him. They completed the work in 32 ...
‘Elvish’ and ‘Farhan’ alone can finish a work in 25 and 50 days, respectively, while ‘Gaurav’ can complete 20% of the job in 10 days. All th...
Two workers A and B were put to some work. If A worked alone, he would have taken 8 hours more than when both A and B had worked together. If B worked a...
P and Q together can do a piece of work in 15 days, Q and R together can do it in 18 days. P starts the work and works on it for 5 days, then Q takes it...
- 22 men can finish a piece of work in 20 days, while 44 women can do the same job in 30 days. How many days will 1 man and 1 woman take to complete the work...
‘A’ alone can complete a work in 20 hours. ‘A’ started the work alone and left after working on it for 15 hours. If ‘B’ completed the rest o...
- Two workers, A and B, can finish a task in 36 days and 48 days respectively, working alone. How many days will they take to complete the work together?
A can do a work in 12 days and B in 16 days. If they work on it together for 3 days then in how many days the remaining work will be completed by B?