      What is the installed capacity of the Tato-I Hydro

      Electric Project approved for Arunachal Pradesh?
      A 186 MW Correct Answer Incorrect Answer
      B 240 MW Correct Answer Incorrect Answer
      C 300 MW Correct Answer Incorrect Answer
      D 500 MW Correct Answer Incorrect Answer
      E 800 MW Correct Answer Incorrect Answer

      Solution

      The Tato-I Hydro Electric Project in Arunachal Pradesh has an installed capacity of 186 MW, with a β‚Ή1,750 crore investment approved by the Cabinet.