A and B individually can complete the work in 30 days and 45 days respectively. If the time taken by C alone to complete the work is 1.5 times the time ...
P can do a piece of work in 10 days, Q can complete double the work in 30 days and R can do the work in 20 days. If all of them together earn Rs. 3900, ...
A takes 32 days to complete a work while B can complete the same work in 12 days less than A. If C can complete 25% of the work in 12 days, then find th...
P alone can finish a piece of work ‘M’ in 8 days while Q takes 4 days to finish it alone. P, Q and R working together can finish the work &l...
- Ayaan and Kabir started working together on a task. Ayaan does 4 units per day and Kabir can finish the full task in 25 days alone. The total work is 100 u...
180 unit of work can be completed by P alone in 30 days. P started working alone and joined by Q after 18 days such that they completed the remaining wo...
- If the efficiency ratio of A, B, and C is 7:9:11, and B and C together can finish a task in 10 days, then how much time will A and B need to complete it?
Komal and Seema individually can complete a task in ‘2a’ hours and ‘7a’ hours respectively. If they together can complete half of the work in 7...
‘A’ and ‘B’ can do a piece of work in 10 days and 15 days, respectively. They started working together but ‘A’ left after 3 days. Find the t...
Arjun, Binny, and Chiku can collaborate to finish a particular task in 12 days. Additionally, Arjun and Binny working together can complete the task in ...