The Sela Pass tunnel which will provide all - weather connectivity to the Indian Army towards the Line of Actual Control ( LAC ) near Tawang near the China border is being constructed at 13,000 feet in Arunachal Pradesh . The construction of the Sela Pass tunnel is being done by Border Roads Organisation ( BRO ). The tunnel will provide smooth vehicular movement . After completion of the tunnel, the distance will be reduced by about 8 - 9 km . Border Roads Organisation Headquarters : New Delhi Director General : Lt . Gen . Rajeev Chaudhary About Arunachal Pradesh Capital : Itanagar Chief Minister : Pema Khandu Governor : B . D Mishra
If 'A' needs 24 more days to complete a certain task working alone compared to when 'A' and 'B' work together, and 'A' is 50% more efficient than 'B', w...
‘A’ can do a piece of work in 12 days. ‘B’ can do 60% of the same work in 18 days. If they work together for the entire time and get paid Rs.154...
30 men can complete a task in 160 days. 12 men start the work and manage to do half of it. Then, 18 more men are added to the team to help finish the wo...
- Raj alone can complete a work in 25 days. Mohan is five times as efficient as Raj. Find the percentage of work completed by Raj and Mohan together in 5 day...
P can do a piece of work in 20 days, Q can complete double the work in 40 days and R can do the work in 30 days. If all of them together earn Rs. 3200, ...
Suppose Y individuals can complete a task in (Y - 28) days, and (Y + 12) individuals can finish the same task in (Y - 32) days, what is the number of da...
‘A’ can do a piece of work in 20 days. ‘B’ can do 80% of the same work in 30 days. If they work together for the entire time and get paid Rs.161...
‘A’ can complete a work in 15 days and is 50% more efficient than ‘B’. ‘A’ and ‘B’ start working together and ‘A’ leaves after 8 day...
The efficiency of P is 80% of the efficiency of Q. If Q can type 150 pages in 30 days, then find the number of days taken by P alone to type 300 pages.
A can finish a job in 20 days while B can finish same job in 30 days. A and B both worked for 5 days and C joins them. In next 3.5 days, all three have ...