Question

Consider the following statements :

I . Taragiri, the third stealth frigate of the Project 17A, was recently launched by Mazagon Dock Shipbuilders Ltd . ( MDL ).

II . The third ship is expected to be delivered by August 2025 .

III . The first ship of Project 17A, Nilgiri, was launched on September 28, 2019, and is expected to begin sea trials in the first half of 2024 .

Which statement / statements is / are correct?

A Only I Correct Answer Incorrect Answer
B Only III Correct Answer Incorrect Answer
C Only II Correct Answer Incorrect Answer
D Only II and III Correct Answer Incorrect Answer
E All I, II and III Correct Answer Incorrect Answer

Solution

Taragiri, the third stealth frigate of the Project 17A, was launched by Mazagon Dock Shipbuilders Ltd . ( MDL ). The ship has been built using integrated construction methodology which involves hull blocks construction in different geographical locations and integration / erection on slipway at MDL . The keel of Taragiri was laid on September 10, 2020, and the ship is expected to be delivered by August 2025 . The estimated cost of Project 17A is around ₹25,700 crore . The first ship of Project 17A, Nilgiri, was launched on September 28, 2019, and is expected to begin sea trials in the first half of 2024 . The second ship of P17A class Udaygiri was launched on May 17 this year and is expected to start the sea trials during the second half of 2024 . The keel of the fourth and the final ship was laid on June 28 .

Practice Next
×
×