P alone can finish a piece of work ‘M’ in 6 days while Q takes 3 days to finish it alone. P, Q and R working together can finish the work &l...
25 men can complete a piece of work in 13 days. One man starts the work and after every day one more man joins the work and this continues till the work...
Ram can do a piece of work in 12 days and Shyam can do the same work in 16 days. They both started work together, Ram left 2 days before the completion ...
A and B together can do a piece of work in (p-8.8) days.The efficiency of D is 10% less than the efficiency of B. A and C together can do the same piece...
Efficiency of A, and B are in the ratio of 3 : 4. If both can do a work together in 30 days. Find out how much days A will take to complete the work alone?
A alone work for 6 days then left the work and B alone finishes remaining work in 12 days. If ratio of time taken by A alone to B alone to finish work ...
A and B can complete a work together in 18 days. If A alone can complete one-third of the work in ‘x’ days and remaining work is completed b...
A work can be completed by ‘A’ and ‘B’, alone in 18 days and 12 days, respectively. Find the number of days taken by ‘C’ to complete the sam...
A can complete `1/4` of a work in 6 days and B can complete `2/5` of the work in 12 days. In how many days can both A and B together complete the work?<...
A and B together can complete a piece of work in 48 days while B and C together can complete the same work in 58 days. All of three together can complet...