Question

A real estate developer wants to evaluate how each additional day of construction stoppage due to a labour strike affects project operations and costs. Which technique is best suited for this assessment?

A Needs Risk Analysis
B Business Impact Analysis
C Cost-Benefit Analysis
D Root Cause Analysis