      Question

      What is the maximum limit to the cost overrun arising

      on account of extension in DCCO, being funded by a Standby Credit Facility, sanctioned at the time of initial financial closure of the project?
      A 5% Correct Answer Incorrect Answer
      B 7.5% Correct Answer Incorrect Answer
      C 10% Correct Answer Incorrect Answer
      D 12.5% Correct Answer Incorrect Answer
      E 15% Correct Answer Incorrect Answer

      Solution

      Explanation: In cases where lenders have specifically sanctioned a ‘ Standby Credit Facility (SBCF) at the time of initial financial closure to fund cost overruns arising on account of extension in DCCO, they may fund cost overruns as per the agreed terms and conditions up to a maximum of 10% of the original project cost. However, in cases where Standby Credit Facility was not sanctioned at the time of financial closure, or was sanctioned but not renewed subsequently, such additional funding shall be priced at a premium to what would have been applicable on a pre-sanctioned Standby Credit Facility. An AIFI shall ensure that the loan-contracts ab-initio specify the additional risk premium to be charged on such Standby Credit Facility, which may be revised upwards based on actual risk assessment at the time of sanction of such facilities.