Question
What is the maximum limit to the cost overrun arising
on account of extension in DCCO, being funded by a Standby Credit Facility, sanctioned at the time of initial financial closure of the project?Solution
Explanation: In cases where lenders have specifically sanctioned a ‘ Standby Credit Facility (SBCF) at the time of initial financial closure to fund cost overruns arising on account of extension in DCCO, they may fund cost overruns as per the agreed terms and conditions up to a maximum of 10% of the original project cost. However, in cases where Standby Credit Facility was not sanctioned at the time of financial closure, or was sanctioned but not renewed subsequently, such additional funding shall be priced at a premium to what would have been applicable on a pre-sanctioned Standby Credit Facility. An AIFI shall ensure that the loan-contracts ab-initio specify the additional risk premium to be charged on such Standby Credit Facility, which may be revised upwards based on actual risk assessment at the time of sanction of such facilities.
Consider the following statements about Kisan Vikas Patra (KVP):
1. The interest rate is 7.5% per annum.
2. The minimum deposit is ₹1000...
Which portal has been recently launched by the National Internet Exchange of India?
Identify the element with an electronic configuration 2,8,1 from among the following options.
- Where is the Moin-ul-Haq Stadium situated?
Who won the 2024 Nobel Prize in Physics?
- Alyavathi Langkumer has recently been appointed as India’s ambassador to which country?
The Solvent Extractor’s Association of India (SEA) and Association of Vegetable Oil Industries (ABIOVE) have signed a memorandum of understanding (MoU...
Consider the following statements about unemployment:
1. Frictional unemployment occurs due to short-term transitions in the labor market.
Recently, who chaired the first Governing Board meeting of the newly formed Anusandhan National Research Foundation (ANRF)?
Match the following correctly: