      In which model of PPP does the private player operate

      and maintain the project while the ownership remains with the government?
      A Build-Own-Operate (BOO) Correct Answer Incorrect Answer
      B Build-Own-Operate-Transfer (BOOT) Correct Answer Incorrect Answer
      C Design-Build-Finance-Operate (DBFO) Correct Answer Incorrect Answer
      D Operation and Maintenance (O&M) Correct Answer Incorrect Answer
      E Build-Transfer-Operate (BTO) Correct Answer Incorrect Answer

      Solution

      In the O&M model, the private player is responsible for operating and maintaining the project while ownership remains with the government. This model is commonly used for toll roads where the private player collects toll revenue.