    • Question

      When IRR equals the cost of capital, what will be the

      value of NPV?​
      A NPV is at its maximum Correct Answer Incorrect Answer
      B NPV is zero Correct Answer Incorrect Answer
      C NPV is negative Correct Answer Incorrect Answer
      D IRR will be undefined Correct Answer Incorrect Answer
      E Project is risk-free Correct Answer Incorrect Answer

      Solution

      The correct answer is B