Question

Once the project is approved and moves into the planning stage, what happens in the next phase of the project life cycle?

A Agreements for risk sharing need to be concluded. B. C. D.
B The total risk on the project typically reduces as activities are performed without loss.
C Risks must be weighed against the potential benefit of the project’s success in order to decide if the project should be chosen.
D Risks are identified with each major group of activities.
E None of these